1. Locate bus connection (HPT and FP only) and
cable as shown. Cut end of cable at angle to
aid in piercing grommet. Leave additional cable
for expansion loop.
3. Slide expediter toward pipe and route cable
through support base entry.
4. Insert banding guide into expediter and snap
into place.
5. Mount expediter to pipe using pipe band. Do
not band over cable.
2. Insert cable into expediter. If mounted on
bottom of pipe, punch out weep hole.
6. Cut off end of cable.
7. Terminate cable with appropriate SCTK
termination kit. Refer to SCTK installation
instructions. Push excess cable back through
expediter. Remove braid pigtail. Tape cable
expansion loop to pipe.
50mm
(2")
Max.
300mm
(12")
Bus
Connection
Weep Hole
101mm
(4") Min.
Do Not Band
Over Cable
25mm
(1") Min.
Expediter
Assembly
Boot
Wire Crimp
Heating Cable
Light Module
Light Module
Wiring
Wiring Details for LED Light
LED Light PigtailHeating Cable
8. Connect heating cable to light module wires
using small crimps. Discard large crimp. See
wiring details.
Expediter
Terminator
TM
ZE-B Beacon INSTALLATION PROCEDURES